Protect your lien rights on every Virginia construction project. Our Notice of Intent service ensures you meet all statutory requirements and preserve your right to file a mechanics lien.
Free Tool
Free, no signup. Virginia statute-accurate.
Must send 30 days before filing lien, but no later than 30 days after completion
90 days from last furnishing labor or materials
Research, preparation, certified mail & proof of delivery
Virginia does not require a preliminary notice. However, a Notice of Intent to File a Lien must be sent to the owner at least 30 days before filing the mechanics lien, but no later than 30 days after the work is completed.
In Virginia, you must file your mechanics lien within 90 days from the last day you performed work or furnished materials to the project.
General contractors, subcontractors, laborers, and material suppliers who have performed work or furnished materials for a construction project in Virginia can file a mechanics lien.
Virginia's Notice of Intent is a required document that must be sent to the property owner before filing a mechanics lien. It must be sent at least 30 days before filing the lien, giving the owner a chance to resolve the payment issue.
In Virginia, you must file a lawsuit to enforce your mechanics lien within 6 months of recording the lien. If you don't file suit within this period, the lien becomes unenforceable.
In Virginia, mechanics liens are filed with the Clerk of the Circuit Court in the county or city where the property is located. The lien must be properly recorded to be enforceable.