State Lien Law Learning Center
Comprehensive guides to mechanics lien and preliminary notice requirements for every state. Stay compliant and protect your lien rights.
Quick Navigation
Washington
RCW 60.04.011 et seq.
Notice Required
Notice Deadline
60 Days
Lien Filing Deadline
90 days after completion
Public Bond Threshold
$200,000 for public projects
Overview
Washington requires a Notice to Customer with detailed owner protection language within 60 days of first furnishing.
Who Must Send Notice
- Subcontractors
- Material suppliers
- Equipment lessors
Who Receives Notice
- Property owner
Key Requirements
- 160-day Notice to Customer deadline
- 2Notice must include owner protection warnings
- 390-day lien filing deadline
- 4Claim of lien must be recorded
Important Notice
Washington's notice includes detailed information helping owners understand and protect their rights.
Timeline Summary
1
First Furnishing
Day 0
2
Notice Deadline
Day 60
3
Lien Filing
90 days after completion
4
Enforcement
8 months from recording to foreclose