50 State Resource

State Lien Law Learning Center

Comprehensive guides to mechanics lien and preliminary notice requirements for every state. Stay compliant and protect your lien rights.

Quick Navigation

Oregon

ORS 87.001 et seq.

Notice Required

Notice Deadline

8 Days

Lien Filing Deadline

75 days after completion

Public Bond Threshold

$100,000 for public projects

Overview

Oregon has one of the shortest preliminary notice deadlines at just 8 business days. The notice must follow specific statutory format.

Who Must Send Notice
  • Subcontractors
  • Material suppliers
  • Equipment lessors
Who Receives Notice
  • Property owner
  • General contractor
  • Construction lender
  • Mortgagee
Key Requirements
  • 18-day (business) preliminary notice deadline
  • 275-day lien filing deadline
  • 3Extended notice format with owner warnings
  • 4Must include information for owner protection
Important Notice

Oregon's 8-business-day deadline requires immediate action. The notice includes detailed owner protection information.

Timeline Summary
1

First Furnishing

Day 0

2

Notice Deadline

Day 8

3

Lien Filing

75 days after completion

4

Enforcement

120 days from recording to foreclose

Need help with Oregon notices?

Our experts can handle your preliminary notice requirements.