Comprehensive guides to mechanics lien and preliminary notice requirements for every state. Stay compliant and protect your lien rights.

Quick Navigation

North Carolina

N.C. Gen. Stat. § 44A-7 et seq.

Notice Required

Notice Deadline

120 Days

Lien Filing Deadline

120 days after last furnishing

Public Bond Threshold

$300,000 for public projects

Overview

North Carolina requires a Notice of Subcontract for subcontractors and suppliers to preserve lien rights.

Who Must Send Notice
  • Subcontractors
  • Material suppliers
Who Receives Notice
  • Property owner
  • General contractor
Key Requirements
  • 1Notice of Subcontract required
  • 2120-day deadline from first furnishing
  • 3Claim of Lien on Real Property filed
  • 4Residential projects have consumer protections
Important Notice

North Carolina's Notice of Subcontract is filed, not just sent to the parties.

Timeline Summary
1

First Furnishing

Day 0

2

Notice Deadline

Day 120

3

Lien Filing

120 days after last furnishing

4

Enforcement

180 days from completion to enforce