Florida

Fla. Stat. Chapter 713

Notice Required

Notice Deadline

45 Days

Lien Filing Deadline

90 days after final furnishing or after Notice of Termination

Public Bond Threshold

$300,000 for state projects

Overview

Florida's Construction Lien Law (Chapter 713) is one of the most detailed in the nation. The Notice to Owner is critical for preserving lien rights.

Who Must Send Notice
  • Subcontractors
  • Sub-subcontractors
  • Material suppliers
  • Laborers
Who Receives Notice
  • Property owner
  • General contractor
  • Lender
Key Requirements
  • 145-day Notice to Owner deadline is strictly enforced
  • 2Notice must contain specific statutory warnings to owner
  • 3Notice of Commencement provides key project information
  • 4Contractor's Final Payment Affidavit releases sub liens
  • 5Fraudulent lien claims are criminally punishable
Important Notice

Florida expanded its contractor definition in 2023 to include construction management and program management services. Material suppliers have enhanced surety claim rights.

Timeline Summary
1

First Furnishing

Day 0

2

Notice Deadline

Day 45

3

Lien Filing

90 days after final furnishing or after Notice of Termination

4

Enforcement

1 year from recording to foreclose