State Lien Law Learning Center

Comprehensive guides to mechanics lien and preliminary notice requirements for every state. Stay compliant and protect your lien rights.

Quick Navigation

Delaware

Del. Code Ann. tit. 25, § 2701 et seq.

No Notice Required

Notice Deadline

30 Days

Lien Filing Deadline

30 days after substantial completion

Public Bond Threshold

$50,000 for public projects

Overview

Delaware has a relatively short 30-day deadline for filing mechanics liens. No preliminary notice is required, but prompt action is essential.

Who Must Send Notice
  • Subcontractors
  • Material suppliers
Who Receives Notice
  • Clerk of Superior Court
Key Requirements
  • 1No preliminary notice required
  • 2Very short 30-day filing deadline from completion
  • 3Statement of claim must be filed with court clerk
  • 4Lien binds only the improvement, not the land
Important Notice

Delaware's 30-day deadline is one of the shortest in the country. Act immediately upon project completion.

Timeline Summary
1

First Furnishing

Day 0

2

Notice Deadline

Day 30

3

Lien Filing

30 days after substantial completion

4

Enforcement

1 year from filing to enforce

Need help with Delaware notices?

Our experts can handle your preliminary notice requirements.