California

Cal. Civ. Code §§ 8200-8216 (Private) / §§ 9300-9366 (Public)

Notice Required

Notice Deadline

20 Days

Lien Filing Deadline

90 days after completion (direct contractors) or 90 days after Notice of Completion

Public Bond Threshold

$25,000 for public projects

Overview

California has one of the most comprehensive mechanics lien systems in the country. The 20-Day Preliminary Notice is essential for preserving lien rights.

Who Must Send Notice
  • Subcontractors
  • Material suppliers
  • Equipment lessors
  • Laborers
Who Receives Notice
  • Property owner
  • General contractor
  • Construction lender
Key Requirements
  • 120-day notice required to preserve full lien rights
  • 2Late notice only protects work done 20 days before notice
  • 3Stop Payment Notice available for private and public works
  • 4Notice of Completion shortens lien filing deadline
  • 5Direct contractors don't need preliminary notice but must file lien within deadlines
Important Notice

California requires electronic recording in many counties. The state has both 'mechanics lien' and 'stop payment notice' remedies.

Timeline Summary
1

First Furnishing

Day 0

2

Notice Deadline

Day 20

3

Lien Filing

90 days after completion (direct contractors) or 90 days after Notice of Completion

4

Enforcement

90 days from recording to enforce