State Lien Law Learning Center

Comprehensive guides to mechanics lien and preliminary notice requirements for every state. Stay compliant and protect your lien rights.

Quick Navigation

Arizona

A.R.S. § 33-992.01 et seq.

Notice Required

Notice Deadline

20 Days

Lien Filing Deadline

120 days after completion

Public Bond Threshold

$150,000 for state projects

Overview

Arizona's 20-Day Preliminary Notice is mandatory for most claimants. The state has detailed requirements about notice content and delivery methods.

Who Must Send Notice
  • Subcontractors
  • Material suppliers
  • Design professionals
Who Receives Notice
  • Property owner
  • General contractor
  • Construction lender
Key Requirements
  • 120-day notice preserves full lien rights
  • 2Late notices only protect amounts furnished 20 days before notice
  • 3Owner must forward notice to lender within 10 days
  • 4Design professionals (architects, engineers) have lien rights
Important Notice

Arizona requires specific statutory language in the preliminary notice. Using incorrect forms may invalidate your lien rights.

Timeline Summary
1

First Furnishing

Day 0

2

Notice Deadline

Day 20

3

Lien Filing

120 days after completion

4

Enforcement

6 months from recording to foreclose