Arkansas

Ark. Code § 18-44-101 et seq.

Notice Required

Notice Deadline

75 Days

Lien Filing Deadline

120 days after last furnishing

Public Bond Threshold

$20,000 for public projects

Overview

Arkansas mechanics lien law requires a lien to be recorded within 120 days of last furnishing materials or labor.

Who Must Send Notice
  • Subcontractors
  • Material suppliers
Who Receives Notice
  • Property owner
Key Requirements
  • 1Lien must be filed within 120 days of completion
  • 2Written notice to owner recommended but timing flexible
  • 3Lien attaches to building and land
  • 4Owner acknowledgment on notice strengthens claim
Important Notice

Arkansas allows owner signature acknowledgment which strengthens the lien claim.

Timeline Summary
1

First Furnishing

Day 0

2

Notice Deadline

Day 75

3

Lien Filing

120 days after last furnishing

4

Enforcement

15 months from filing to enforce

Need help with Arkansas notices?