Comprehensive guides to mechanics lien and preliminary notice requirements for every state. Stay compliant and protect your lien rights.
Quick Navigation
Alabama
Ala. Code § 35-11-210 et seq.
Notice Required
Notice Deadline
30 Days
Lien Filing Deadline
6 months after completion or abandonment
Public Bond Threshold
$100,000 for public projects
Overview
Alabama's mechanics lien law provides protection for contractors, subcontractors, and material suppliers who improve real property. The law requires timely preliminary notices to preserve lien rights.
Who Must Send Notice
- Subcontractors
- Material suppliers
- Laborers
Who Receives Notice
- Property owner
- General contractor
Key Requirements
- 1Preliminary notice must be sent within 30 days of first furnishing
- 2Lien must be filed within 6 months of completion
- 3Notice must be sent via certified mail
- 4Residential and commercial projects have same requirements
Important Notice
Alabama increased its public bond threshold from $50,000 to $100,000 in recent legislation.
Timeline Summary
1
First Furnishing
Day 0
2
Notice Deadline
Day 30
3
Lien Filing
6 months after completion or abandonment
4
Enforcement
6 months from filing to enforce lien