State Lien Law Learning Center

Comprehensive guides to mechanics lien and preliminary notice requirements for every state. Stay compliant and protect your lien rights.

Quick Navigation

Alaska

AS 34.35.050-120

Notice Required

Notice Deadline

15 Days

Lien Filing Deadline

120 days after completion

Public Bond Threshold

$100,000 for public projects

Overview

Alaska requires a Notice of Right to Lien to be filed within 15 days of first furnishing. This is one of the shorter preliminary notice deadlines in the country.

Who Must Send Notice
  • All potential lien claimants
Who Receives Notice
  • Property owner
  • Prime contractor
Key Requirements
  • 115-day preliminary notice deadline is strictly enforced
  • 2Notice must identify the property and describe materials/labor
  • 3Lien filing deadline is 120 days after completion
  • 4Stop notices available for public and private projects
Important Notice

Alaska's short 15-day deadline requires immediate action upon starting work.

Timeline Summary
1

First Furnishing

Day 0

2

Notice Deadline

Day 15

3

Lien Filing

120 days after completion

4

Enforcement

6 months from recording to enforce